Tuesday, September 20, 2011

FLOOR TILE

 Loft bathroom, girls bathroom and laundry room


Master bathroom Honed Carrara Marble

Thursday, September 15, 2011

COUNTERTOPS INSTALLED

Serena "washing" her hands in her new sink
All the countertops and sinks were being installed in the house today.  They look great!
 
 



Below: cabinet doors awaiting handles and installation


In floor heating installation in master ensuite prior to tile work.
The tile is all sitting in the front room waiting for install next week!

Sunday, September 4, 2011

CONCRETE POURED FOR SIDEWALK


HOUSE PROGRESS.....

Glass rails have been installed, they look great against the stained staircase

Staining throughout the house is completed.  

 Laquering of the built in furniture and window/door casings

Lacquering the lockers in the mudroom and front entry panelling

Basement panelling

Saturday, August 13, 2011

EXTERIOR

 Hardie board is being installed
 Prepping rear driveway for concrete
 Re-bar placed prior to concrete pour, east side of house

STAINING THE WOODWORK

 The staining is being worked on now and they will begin prepping for painting next week. It's looks great!